November 2019 - Work starts
Work started on 5 November with the demolition of the rear conservatory and the utility lean-to. The kitchen and upstairs bathroom were stripped and the floor between them removed. Water pipes, radiators and electric cables were also taken out. What used to be the kitchen! Where the upstairs bathroom used to be The first of many skips No more lean-to utility space ...and no more conservatory And then it was time to dig out the footings After a rather panicky day on Friday making sure there were no cars opposite, the concrete lorries arrived at 7.30 am on Saturday 16 November. After one of them reversed into the gatepost (leaving rear lights behind) and a puncture, the concrete was finally poured into the foundations. It all then went quiet for a while apart from the scaffolding being put up and the delivery of the blocks.