A good start to the New Year

Image
The good progress continued in January.   As at 21 January: The rear initial terrace work was completed so that some of the rubble could be held in the retaining walls.   Where did the lawn go? The limestone facing was delivered from the quarry: The team had a big job getting them all dressed - it sounded (and looked) like a Victorian penal colony! Some serious demolition was done above the old dining room - the roof was completely removed and the doorway to the planned mezzanine knocked through:   The steel joists were also delivered and the first fitted above the dining room to take the mezzanine bridge:

And so onwards into 2020!

Image
Form mid-December through to the New Year there was very good progress due ti a combination of  continuing hard work by Dan and the team and good weather - note there is actually some blue sku in the following photos! The roof on the North side of the roof was completed: The blockwork on the kitchen really took shape right up to having the roof joists in place:   NB Blue sky!     The rear extension blocks were also completed up to the point of the future bedroom floorboarding in place:         During this period we also had the internal sand blasting done so that the plaster would fix well to the inside walls.  This created an awfully lot of ...