A good start to the New Year
The good progress continued in January. As at 21 January: The rear initial terrace work was completed so that some of the rubble could be held in the retaining walls. Where did the lawn go? The limestone facing was delivered from the quarry: The team had a big job getting them all dressed - it sounded (and looked) like a Victorian penal colony! Some serious demolition was done above the old dining room - the roof was completely removed and the doorway to the planned mezzanine knocked through: The steel joists were also delivered and the first fitted above the dining room to take the mezzanine bridge: